Is an Engineer ever immune from lawsuit? (Law note)

Spokane city towerCan an Engineering firm be held liable in negligence despite provisions in a state law which allegedly gives design professionals immunity?  That was the issue confronted recently by the Supreme Court in the state of Washington in a case entitled Larry Michaels vs. CH2M Hill.

The Washington court analyzed its state Industrial Insurance Act, which is similar to North Carolina’s Workers’ Compensation Act.  These acts are often described as “grand compromises” between workers and their employers.  Injured workers are given a fast, no-fault compensation system for injuries in the workplace. Employers, in turn, are given immunity from civil suits.  The workers get speed and certainty, while the employers are required to pay less than they would be in a lawsuit.

Washington state’s Act, unlike North Carolina’s Act, provides some immunity for design professionals performing design services, and the court had to wrestle with the applicability in a particularly gruesome case involving a catastrophic failure at the Spokane wastewater treatment plant.

One man was killed and another two other seriously injured in May 2004 when a digester dome (a huge, sports stadium-like contraption) collapsed at the wastewater treatment plant. The collapse caused Mr. Cmos to fall into heated sewage sludge, where he drowned. The lower court judge described the incident as arguably one of the most disgusting and terrible deaths imaginable. Mr. Evans was thrown from the dome and drenched with the sewage, while Mr. Michaels was knocked down by a cascade of sludge. The survivors, and the family of Cmos, sued CH2M for negligence.

CH2M was an engineering firm hired by Spokane as a consultant on a 10-year capital improvement project to upgrade the plant. One of the tasks the engineering firm oversaw was replacement and re-engineering of several transfer tubes between various digester domes at the plan. Ultimately a buildup of sewage occurred, shattering the dome on digester #3 and fatally injuring Cmos.

A series of unfortunate events took place on that day in early May of 2004 that all conspired to lead to the sewage buildup. After failed attempts to transfer the sludge to another digester, foam began leaking out of a pressure relief valve at the top of dome #3. The effluent ran down the outside of the dome and a concerned plant superintendent worried that the discharge might enter the Spoken River. The supervisor gathered Cmos, Evans and Michaels and asked if the three could assist him in diverting the sludge. Cmos and Evans climbed the dome with a fire hose to siphon foam while the superintendent and Michaels attached the other end of the house to a drain.

The dome continued filling with sludge until it finally cracked and collapsed. Cmos, alive and conscious, dropped into 100 degree sewage sludge and died in excruciating physical pain, darkness and utter helplessness. Evans and Michaels suffered varying severe injuries including broken limbs and lung damage from aspirating the sewage.

The city hired an engineering firm to investigate the disaster. The firm concluded there were three main causes: 1) a blocked overflow pipe; 2) a malfunctioning monitoring system inside the digester; and 3) a failed attempted to transfer sludge out of the digester.

Tomorrow, we’ll discuss the Court’s analysis and ruling concerning whether or not CH2M had immunity from being sued, and Friday we’ll discuss a few take-away lessons from the case.  Stay tuned……

Have you signed up for the blog to be delivered directly to your in-box? If not, do so now, so you’ll be sure to catch parts 2 and 3 of this article, and never miss any other posts here, either.

Photo: (c) spokanephotos.com via Creative Commons license.

Developers Rejoice Over Impact Fees Decision (news note)

Today I’m unveiling a new column here at Construction Law in North Carolina called “News Notes”.  News notes will be postings of current news items relating to the design (and construction) community.  [This means that sometimes I must be a tad drier than my usual festive self.  Consider yourself warned.]  If you have an idea for a News Note, drop me a line.

Much to the delight of developers and realtors across the state, the North Carolina Supreme Court recently affirmed a decision which struck down local school impact fees. The fees had been assessed to fund construction of new schools in the Cary portion of the Wake County schools to help with the Town ofCary’s  rapid growth.

Impact fees are usually enacted by local boards and town councils as Adequate Public Facilities Ordinances (APFO).  In 1999, the Town of Cary began assessing school impact fees on developers in certain portions of the town which faced overcrowding.  The revenue brought in by the fees was earmarked to pay for expansion of existing school facilities.  Notably, the Town of Cary has no separate school system from the rest of Wake County, and did not have the legal authority to control the provision of school facilities within the district.

Last month, the state Supreme Court, in a tight 3-3 tie decision (with one abstention) left the Court of Appeals decision in place, rejecting the Town’s attempt to collect school facilities fees and declaring the fees illegal.  [As an aside, my firm represented another developer who intervened in the lawsuit; however, the facts were somewhat different and we were not involved in this appeal.]

The Cary case is not the first time the issue has arisen in the state.  Currituck County once proposed a similar APFO to fund school construction during the real estate boom as out-of-state residents from Virginia crossed into North Carolina in an attempt to flee the taxes and dismal school system in Chesapeake,Virginia.

The Currituck proposal was widely criticized by both local and state homebuilder’s associations. Across North Carolina, homebuilders and realtor groups worked together to stop attempts at passing such impact fees. These organizations have run into problems as cash-strapped local governments see impact fees as one method of paying for increasingly expensive public school construction.

The theory is that developers of new homes pass the impact fees along to new home buyers by raising the price of homes or lots. Existing residents are spared the tax increases caused by a rapid influx of new residents with school-aged children. Thus, the people responsible for the increased strain on the school system – the new residents – bear the burden of the tax increase.

school

 

Over the past decade, Durham, Union County, and Cabarrus County have instituted similar impact fees. All three such attempts were disallowed by various courts. Thus far, virtually all attempts at imposing such fees have been struck down, although there appears to be wiggle room in the case law. For example, impact fees collected for improvements that directly run to the property (such as water or sewer lines) are typically allowed. Additionally, other municipal governments impose fees related to schools that have not (yet) been decided in the state court system, and those may be broad enough to pass judicial scrutiny.

In this case, Cary’s ordinance assessed residential developments a mitigation fee if they did not first obtain a certificate from Wake County certifying classroom availability. Over $4 million was ultimately collected since the ordinance was first passed in 1999. Cary is now faced with the prospect of returning these fees, plus over $300,000 in attorney fees awarded to the developers who filed suit.  Ouch!!!

Comments or questions?  Post in the comment section, below.

Photo (c) Ivy Dawned via Creative Commons license.

Standard of Care for Engineers- the Jury Instruction (law note)

Not perfection I’ve previously talked about the standard of care for design professionals on construction projects. 

As you should be aware, the standard is reasonableness, not perfection.  To illustrate the point, consider a standard North Carolina jury instruction on the standard of care for engineers:

 “Under our law, a professional engineer is required to exercise that degree of care which a professional engineer of ordinary skill and prudence would exercise under the same or similar circumstances, and if the engineer fails to exercise such degree of ordinary skill and prudence under the same or similar circumstances, the engineer’s conduct would be negligence.”

For an architect, just substitute the word “architect” for “engineer” in the jury instruction above.    Sometimes it can be challenging to meet a client’s expectations, and some clients believe that plans should (and can) be perfect.  In your discussions about the project with the client, be sure the client has reasonable expectations.  It is not reasonable to expect perfection in design plans.  Unforeseen conditions, changing criteria, and differing code inspector interpretations are all to be expected.  Educate your client about typical errors & omissions at the start of the construction project.
 
Do you have a question about the standard of care?  Drop me an email at mbrumback@rl-law.com.  Be sure to sign up for email delivery of blog posts directly to your inbox so you never miss a post!
 

Safe Harbors- not just for Sailors anymore (or, why advance planning can prevent claims of defective plans & specs) (law note)

Have you ever considered a “Safe Harbor Provision” for your Owner-Architect or Owner-Engineer contract?  Maybe it is time that you do.

As you are (probably too well) aware, on every construction project there are changes.  Some of these are due to the owner’s change of heart, value engineering concerns, contractor failures, and material substitutions.  Some may be because of a design error, omission, or drawing conflict.  It happens.

safe harbor provisions

A “Safe Harbor Provision” is a provision that establishes an acceptable percentage of increased construction costs (that is, a percentage of the project’s contingency).  The idea is that if the construction changes attributable to the designer is within this percentage, no claim will be made by the Owner for design defects. 

An example provision is provided in the EJCDC documents (Exhibit I, Allocation of Risks, of  Form E-500), which provides

Agreement Not to Claim for Cost of Certain Change Orders: Owner recognizes and expects that certain Change Orders may be required to be issued as the result in whole or part of imprecision, incompleteness, errors, omissions, ambiguities, or inconsistencies in

the Drawings, Specifications, and other design documentation furnished by Engineer or in the other professional services performed or furnished by Engineer under this Agreement (“Covered Change Orders”). Accordingly, Owner agrees not to sue or to make any claim directly or indirectly against Engineer on the basis of professional negligence, breach of contract, or otherwise with respect to the costs of approved Covered Change Orders unless the costs of such approved Covered Change Orders exceed __% of Construction Cost, and then only for an amount in excess of such percentage. Any responsibility of Engineer for the costs of Covered Change Orders in excess of such percentage will be determined on the basis of applicable contractual obligations and professional liability standards. For purposes of this paragraph, the cost of Covered Change Orders will not include any costs that Owner would have incurred if the Covered Change Order work had been included originally without any imprecision, incompleteness, error, omission, ambiguity, or inconsistency in the Contract Documents and without any other error or omission of Engineer related thereto. Nothing in this provision creates a presumption that, or changes the professional liability standard for determining if, Engineer is liable for the cost of Covered Change Orders in excess of the percentage of Construction Cost stated above or for any other Change Order. Wherever used in this paragraph, the term Engineer includes Engineer’s officers, directors, members, partners, agents, employees, and Consultants.

 [NOTE TO — USER: The parties may wish to consider the additional limitation contained in the following sentence.]

Owner further agrees not to sue or to make any claim directly or indirectly against Engineer with respect to any Covered Change Order not in excess of such percentage stated above, and Owner agrees to hold Engineer harmless from and against any suit or claim made by the Contractor relating to any such Covered Change Order.

[Emphasis added to key provisions by me].

Essentially, the EJCDC safe harbor provision includes the following:

  • Owner’s acknowledgement that change orders are standard operating procedure on construction projects
  • Owner’s agreement not to sue or bring any claims against the engineer  unless the costs of such exceed a negotiated percentage of the construction cost.
  • Owner’s acknowledgment that not all change orders over the allocated percentage are the designer’s responsibility, as the aggregate amount does not include costs that the project owner would have incurred if the work covered by the change order had been included originally (the “betterment” to the owner).
  • Owner’s acknowledgement that only the overages attributable to the design are compensable — notably, nothing changes the professional liability standard for determining if the engineer is liable in excess of the percentage. 

Again, this is one of those “don’t try this at home” moments.  A poorly written safe harbor provision could do more harm than good.  It may be seen as establishing a warranty, and that would be an uninsurable loss.  If not properly crafted, it may create the expectation that all overages fall on the designer.  Proceed with caution!

When well-drafted, however, a safe harbor provision can provide you with some level of comfort for the inevitable discoveries that happen when the drawings hit the pavement.

 Have you ever used a “safe harbor” provision in your Owner-Designer agreement?  Did it work to your advantage, or did it create unreasonable expectations that change orders were capped at that amount?  Share your experience below.

———————-

Photo: Boats in safe harbor, Roseau, Dominica via teletypeturtle/Creative Commons license.

Wine without Cheese? (Why a construction contract needs an order of precedence clause)(Law Note)

wine and cheese

Reader Mailbag:

For today’s law note, I’m addressing a comment that came to me last week from Dave O’Hern of Miller O’Hern Construction.  Dave writes:

I am a general contractor doing a fuel tank replacement project for our county. In the specifications there is a spec for a UL 142 tank, on the plans the spec references UL 2085 – a much more expensive tank. My subcontractor bid the UL 142 tank. The specifications state that the specs and plans are on the same level of precedence.

The county wants me to furnish the more expensive tank without compensation citing the clause that states the plans and specs are complementary and what is called for by one is binding as if called by all and the most stringent requirement will apply.

My position is the word “stringent” according to Websters means “rigidly controlled, enforced, strict, severe.” The two specifications are written by Underwriter’s Laboratory and precisely decribe each type of tank clearly and without ambiguity for the purpose of rigidly controlling the qualities of the product. Consequently the two specifications are equally stringent. Stringent does not mean more expensive or what the pre-bid intent of the owner.

Is this sound reasoning, does it fall under Spearin and is there another defense I should take?

What Dave is experiencing is a poorly-constructed contract.  Obviously, the goal in a set of construction documents is to not have any conflicts.  However, between specifications, drawings, shop drawings, contract language, addendum, and change orders, the goal of absolute consistency in contract documents is impossible extremely hard to meet.

The usual way around this very likely problem is to state the order of precedence of the various contract and construction documents, so that in the event of a conflict between two provisions, everyone knows which one prevails.  In the absence of any contract language stating the order of precedence, the parties are forced to argue contract law principles such as mutual mistake, which party is considered the contract drafter (and hence, disfavored), and other technical legal issues that numb the mind are only exciting to those of us crazy enough to go into the legal profession.

Sure, you can have wine without cheese, but why would you?  The two should go together, in the same way that an order of precedence clause should go with any construction contract.

Dan has also raised the issue of “more stringent” requirements.  In general, when a contract contains instructions that are susceptible to two or more reasonable interpretations, these are considered “ambiguities”.  There is generally a duty on the contractor to point out conflicts between the documents.  However, where a conflict between the documents is not noticed by any party prior to the bidding, the plans arguably are defective under the Spearin doctrine.

So, back to Dan’s question.  Dan– your situation is a mess!  I agree that your reasoning on the stringent requirements is sound; whether or not a Court will agree with your position remains to be determined.  Time to hire a good construction lawyer in your jurisdiction to negotiate a resolution to your situation!  (I see that you are in Arizona.  If you don’t have a lawyer, let me know and I’ll try to get you a recommendation or two).

Have you ever encountered a contract like Dan’s?  Did it cause any problems with conflicting documents later on?  How did you handle the situation?

—————————

 Photo:  054/365: Wine, cheese and crackers via Addison Berry/Creative Commons license.