Expect the Unexpected (your design contracts in a post-COVID world)

Have you adapted your post-COVID practice to better plan for the “unexpected” ?  In particular, have you looked at–and revised– your professional services contracts to give yourself a little more breathing room for unaccounted issues that may arise?  If not, no time like the present.

Don’t like that saying?  How about ” a stitch in time saves nine?”  No?  Still nothing?  What about a picture of something so completely unexpected it shocks you– say, a fireman commuting home, in fire-fighting regalia, on a tricycle?  Okay, here you go…

Fireman-bikerNow that I have your attention– you should make it a practice to regularly review and update your professional services agreements, and you should consider issues such as:

  1.  Does your agreement provide for extra compensation if you have to spend more time or a longer period providing construction administration services for material delays or labor shortages?  If not, it should.
  2. Does your agreement have a well-written “act of God” provision– one that includes pandemic/epidemics as part of the “act of God” conditions in which a term may become void?  If not, add it now!
  3. Have you considered whether you want arbitration instead of litigation if a lawsuit does arise?  And if you want to arbitrate, does your contract give specifics, like how many arbitrators will decide the case?  These things can be added now with little effort, or you can pay your lawyer to negotiate them down the line.  Guess which is cheaper?

You *do* have a good, solid contract to begin with, correct?  If not, I’ve previously given examples of how to craft helpful scopes of services and how to add the protection of a well-crafted exclusion to your scope of services.   Check them out, and be ready for the next biker-fireman surprise in your future.

Photo (c) MelissaBrumbackCreative Commons License

Are we having fun yet? Construction in a post-COVID world (law note)

Remember how I said to never assume?  Yeah, about that……   even when you plan for failures, mistakes, and other problems, sometimes things get so outside the realm of what you considered that it can leave your construction project spinning.  Take, as a random example, a world-wide pandemic that shuts down supply chains, shuts down job sites, and limits the labor pool.  Just as an example.

What does construction law say about pandemics?  They fall under an “Act of God” that you may have read about in your contracts, or in the contracts of the contractors working your projects.  An “Act of God” is an event that is not foreseeable, and as such not something the parties could have anticipated when they drafted the contract.  Acts of God generally excuse a party’s failure– for example, a contractor’s failure to complete the project on time can be excused when an “act of God” has occurred. 

By now, you’ve dealt with the practical fall out, one way or another.  Many projects no longer made financial sense for your clients.  Others may have been modified, reduced in scope, or had substitute materials put in place.

What do you, as an architect or engineer, do now, faced with the potential for further shut downs, supply chain issues, and other COVID variants?  The short answer is to give yourself options and assume changes will be needed to your own scope of work on each project.  Consider:

  1.  If the project needs to be re-designed to account for shortages, can that be an additional service that you get paid for?
  2. If the project requires substitute products, how many of those are part of your basic service, or is there a point at which you should get paid hourly for researching, reviewing, and approving substitutes?
  3. If the project takes a lot longer than anticipated to complete, whether due to government shut downs, labor issues, or supply chain problems– can you get paid increased contract administration fees?  And, is there a contract provision that allows you to increase your hourly rate after X number of months, to reflect inflation?

These are some of the ways that you, as a designer, can protect yourselves from ongoing delays, and make sure you are not tied to a project without a way to recoup your extra costs.

Thoughts?  Questions?   Share what’s worked for you or what you’d like to learn more about in the comment section below.

 

 

You Cannot Have Your Cake and Eat It, Too! (Estoppel) (law note)

slice of chocolate cake We’ve talked previously about the statute of limitations  here at Construction Law in North Carolina.  A recent North Carolina Court of Appeals case gives a vivid example of one exception to a statute of limitations defense– estoppel. Estoppel is the act of lulling a party into not filing a lawsuit through your actions.  You are then deemed “estopped” from asserting the statute of limitations as a defense. That is, a party cannot use the statute of limitations as a sword to benefit from his own conduct which induced a plaintiff to delay filing suit.  Proof of actual fraud or bad faith is not required; however.  The “basic question” is whether defendant’s actions “have lulled the plaintiff into a false sense of security and so induced [the plaintiff[ not to institute suit in the requisite time period.”  Cleveland Const., Inc. v. Ellis-Don Const., Inc. et al., __ N.C. App. __, 709 S.E.2d 512 (5 April 2011). In that case, the general contractor on a public hospital project, Ellis-Don, asked Cleveland Construction Inc. (CCI), one of its subcontractors, to delay making its own delay claim on the project.  The general contractor sent a letter to CCI  asking it not to sue it in order to present a “unified front” to the State during the State Construction Office’s administrative claims process. The Court found that Ellis-Don affirmatively represented to CCI that it was  pursuing CCI’s claims as part of its overall claim against the State. The Court further found that Ellis-Don affirmatively represented to CCI that CCI should not  initiate a claim because that would jeopardize the success of the total contractor recovery with the State.  As such, Ellis-Don lulled CCI into a false sense of security, as CCI reasonably believed that Ellis-Don would pass through to CCI any proceeds attributable to its claim from Ellis-Don’s settlement with the state.  Ellis-Don was, therefore, equitably estopped from asserting the statute of limitations when CCI later sued Ellis-Don on those same claims.   Here, Ellis-Don tried to benefit from including CCI’s claim in its overall claim at the State Construction Office, and later benefit from CCI’s failure to adhere to the time limits imposed on bringing claims.  The Court held that a contractor cannot have its cake and eat it too.  (After all, too much cake is bad for anyone). Practice Note:  Do not count on the theory of equitable estoppel for untimely claims.  A court could decide you were not reasonable in holding back from initiating legal action, in which case your claim would be denied.   Equitable theories are to prevent injustice, but you cannot and should not rely on them.  Have you ever delayed filing suit on the promises or statements of another party?  Did the Court find the other party was equitably estopped from claiming a statute of limitations defense, or did the Court allow such a claim?  Share your experience in the comments section below.

———————–

Photo:  (c) Dennis Mojado via Creative Commons license.

Why Misery Loves Company (aka Concurrent delay on the Construction Project) (law note)

You know the old saying, “Misery loves company?”  It’s true.  Even in the construction world.

misery license tag

What happens if, while the design team is asleep at the switch, the contractor is also delaying the project, or the owner is dithering about a materials selection?  Since there was more than one cause of the project delay, does that let you off the hook?  Maybe so.

The above scenario is, in its bare-bones basics, an example of concurrent delay.

What is concurrent delay?  Concurrent delay is delay to the critical path of construction, caused at the same time by multiple events not exclusively within the control of one party.  In other words, it is when two or more parties both contribute to the delay of the project.

In such a case, neither may recover damage from each other, unless there is proof of clear apportionment of the delay and expenses.  See Biemann & Rowell Co. v. Donohoe Cos.,147 N.C. App. 239, 245, 556 S.E.2d 1, 5 (2001).

Where both parties contribute to the delay, neither can recover damages, unless there is proof of clear apportionment of the delay and the expense attributable to each party.  In such an instance, the only remedy for both parties may be an extension of time to the contract.

Have you experienced a case where concurrent delays existed on a Project?  Were you able to apportion the delay damages, or did all the culpable parties pay the price?  Share below. 

Also, please sign up for email delivery of blog posts directly to your inbox!

—————————————

Photo: Misery by Molly Helzschlag via Creative Commons license.

The Architect Has No Clothes! (or, why subconsultant contracts matter)

Caesar statute

Everyone is probably familiar with the story the Emperor’s New Clothes.  There, the Emperor is not wearing anything but his birthday suit, and yet everyone is afraid to tell him so.  Today’s lesson is how to avoid being the clothesless fool by making sure you are covered with appropriate contracts with your subconsultants.

Previously we have talked about the need for a written contract on your construction projects.  Usually, the focus is on the contract agreement with the Project Owner.  Just as important, however, is the contract with your subconsultant.

A recent case brought to the attention of the E&O carrier Victor O. Schinnerer demonstrates what can happen when you have a signed contract with the Project Owner, but your subconsultant contract is not yet formalized.

The architect’s subconsultant agreement had been revised by the subconsultant to include the following language: 

Subconsultant’s maximum aggregate liability under this Agreement shall not exceed $250,000.

Having been warned of the dangers of limiting the liability of a subconsultant without having a corresponding limitation in the prime agreement, the architect attempted to further negotiate with the subconsultant. The subconsultant agreed to increase their liability to $500,000 but said “I am told by our legal counsel that based on the work we are doing and the amount of our fee, $500,000 is our limit.  

Work on the project had already started, but the subconsultant was withholding their design documents until they received a signed contract.  At that point, the architect turned to his E&O carrier for advice.

His options were limited at that point, and the architect was left with weighing the risk of a claim in excess of $500,000 versus the risk of a delay claim from the Project Owner if he took time to seek out a new subconsultant.  Essentially, the architect had no clothes.

Keep this lesson in mind the next time you are negotiating with subconsultants about a planned project.  You should ensure that their contract has the same obligations that you have in your contract with the Owner.

Have you experienced a situation where you were contracted to perform, but your subconsultant refused to sign a contract with similar terms? How did you handle it?Drop me a line in the comment section.

—————————

Photo: (c) Mary Harrsch via Flickr/Creative Commons License.