Construction Termination Issues Part 4: What to do when they want to fire you, the architect or engineer

What if you are told that your own design services are no longer needed or welcome on a project?  Can they do that?  What happens then?  How do you protect yourself.

As you probably realize, while rare, the Owner does have the legal right to fire you “for cause”.  See B101 §9.4, as long as the Owner gives you 7 days written notice.  In fact, the Owner can terminate your contract for any reason at all (maybe you root for the wrong basketball team?) by terminating you for convenience (i.e., for any reason whatsoever) under B101 §9.5, again with 7 days written notice.

As with Contractor terminations, the money you get when fired for convenience is much greater than when you are terminated for cause.   If you are fired “for convenience”, you get paid for all services previously rendered as well as termination expenses, including anticipated profit on the value of services not performed. See B101 §9.7.

But, what about when you are terminated for cause?  While unusual, this can–and does– happen.  It means you will not be seeing the lost, but anticipated, profits on the job.  Usually this is not as significant as a contractor termination, as during the construction phase you are presumably being paid monthly pursuant to a written contract.fired executive falls down stairs

If you are being fired, document everything!  Document what has happened, the status of submittals or product samples that you may have but have not yet approved, the pending dates with inspectors—you name it.  Put together a nice letter to the Owner telling them everything currently going on with the project.  This will protect you as much as it protects the owner.

Secondly, notify your subconsultants.  The owner may want them to continue on—you will have to have frank discussions with them about whether they are willing to continue if you are terminated, and in general they will not be able to do so unless you assign the agreement.  This is leverage you can use while exiting stage left—use it to get better termination terms or protections from the Owner.

Finally, if you are being terminated because the Owner does not agree with your pay application or work completed determinations, document those disagreements as well.

Next week, Part 5—what to do when YOU want to be done with it all

Ever been terminated or released from work on a project you designed? It’s never pleasant, but it can be handled.  Share your details below, or shoot me an email. 


Photo (c) and Designed by Wannapik

Construction Termination Part 3: When the contractor is firing the owner

Last week we discussed an Owner terminating a Contractor “for cause”.  Today, it’s time for a 180:  what is your role as the architect when the Contractor is quitting?

First, be aware that there are valid reasons for a contractor to quit within the contract itself. Most of these have to do with either (a) time delays/stand stills or (b) failure of the Owner to make payments as required.

two boxers in ring

Never thought being a designer required Referee skills, did you?

 

The Contractor can suspend or terminate a contract with the Owner for cause, provided a 7 day written notice is given to Owner and Architect.  See A201§14.1.3.  (This can be an email notice as all AIA notice clauses now allow).

If this happens, what do you do?  First, consult with the Owner to see if there is truth in the Contractor’s assertions.  See if payment can be caught up, or any disputed money put into an escrow, or other options that will keep the Contractor working.  Ultimately, if the project comes to a stand-still, money will be lost.  Where money is lost, parties are sued.  Keep the project moving to lower your own risks of being sued.

If there is no way to salvage the situation, make sure to fully document the  Project status at the time the contractor quits work.  Photographs, videos, a line in the file as to how much money had been earned and paid by the termination date.  All will be key evidence in the inevitable law suit.

While the contractor’s decision to quit is out of your hands (you don’t have to certify anything), documenting the state of the Project can only help all parties later on.

Next week, Part 4—when they want to fire You!  (the audacity!). 

Until then, have you seen a contractor walk off a job site?  Did you agree with them?  Were you surprised when it happened?  Share your war stories in the comments, or drop me a line.


Photo © World Series Boxing via Creative Commons License

Construction Termination Part 2: How to handle construction administration when the contractor is getting fired

chameleonIf you’ve been working as a design professional for any length of time, you know that you must be a chameleon on the construction project.  You need to “step into the skin” of both  the Owner and the Contractor to determine who is at fault, and who should pay.

You are usually the Initial Decision Maker (IDM), and so you have a duty under the AIA documents to act fairly and impartially in making those decisions.  See AIA B101§3.6.2.4.

Even if you are not under an AIA contract, you still have that duty if you are the IDM or handling construction administration for the project.  More often than not, however, it will be the owner asking you to support its termination of the contractor “for cause”.

Should you do so?

Before making any decisions, see what the contract says about when a contractor can be fired.  There is usually one set of specific facts that supports this.  In A201§14.2.1, the Owner may terminate the Contractor if the Contractor:

  1. repeatedly refuses or fails to supply enough properly skilled workers or proper materials;
  2. fails to make payment to Subcontractors or Suppliers in accordance with the respective agreements between the Contractor and the Subcontractors or Suppliers;
  3. repeatedly disregards applicable laws, statutes, ordinances, codes, rules, and regulations, or lawful orders of a public authority; or
  4. otherwise is guilty of a substantial breach of a provision of the Contract Documents.

You may have noticed that these are not set formulas.  If job staffing varies from day to day, when does the lack of manpower rise to a justifiable reason to terminate a Contractor for cause?  What if the lack of proper, sufficient material for the jobsite is due to outside forces like lack of manpower in the community due to post-pandemic shortages?  And what is meant by the nebulous phrase “otherwise is guilty of a substantial breach?”

The Owner will be looking to the design professional to certify that one of these “causes” exists.

If you make an independent investigation and decide the Owner does not have “cause”, you can remind the Owner of its ability to terminate “for convenience” at any time.   The difference between “cause” and “convenience” has to do with how much, if any, money the contractor is entitled to from the owner.  Simply put, if it is for convenience of the owner, the contractor will get money for lost profit and opportunity; if he is fired with reason, he may end up owing the Owner money.

When terminating a Contractor for cause, the Owner risks a later finding that its action in terminating the contract was without just cause.  If this happens and you assisted in making the determination that the Owner’s termination was justified, you will be sued.  Almost as sure as the sun sets in the West—if there is a wrongful termination lawsuit, you will be part of it.

So, make the decision carefully, and document, document, document the reasons for it.

First, are there any less drastic steps could be taken?  For example, the Owner could elect to stop further work until a contractor corrects bad construction.  (See AIA A201 §2.4).  Or, the Owner can carry out work itself, with proper notice and a 10 day opportunity to cure.  (See A201 §2.5).  The Owner may not be aware of these options—so point them about if they could stop the nuclear termination option.

Second,  review the contracts to ensure all proper notices are being given.  Prior to termination, the Owner must give a 7 day written notice to the Contractor and, depending on the contract used, an opportunity to cure.  See A201 §14.2.2.   The notice should be given to both the Contractor and any relevant surety. If the Contractor does not begin work to correct the deficiencies within 7 days, then the Owner can terminate the agreement and complete the work through alternative Contractors.  While the notice requirement is the Owners and not yours, tell the owner, in writing, what they must do.

Next week, how to handle construction administration when the contractor is the one doing the firing.

In the meantime, have you ever had to make the convenience v for cause analysis?  How did you do it?  What actions or inactions of the contractor were important to your decision?  Share below.


Photo © Krahulic from Pixabay via Creative Commons License

Construction Termination Issues for the Architect and Engineer: Part 1– Introduction to the Series

Earlier this year, I was asked to talk to other construction lawyers on the topic of termination.  My first question was– whose termination are we talking about here– the architect / engineer?  The contractor?  Is someone wanting to “fire” the owner?  The answer, as it turns out, is — yes.  That is, yes, any and all of the above termination topics were on the table.

As you may have suspected, even the threat of a termination is bad, bad news.  It is the “nuclear option” for a construction project.  Everyone risks getting harmed.  As the design professional administering a contract, you run a risk of being dragged into litigation no matter what you do.  So, how should you proceed?  Carefully.

Elmer Fudd and dead Daffy Duck

As Elmer Fudd would say, be very, very careful!

To start, follow along in my new limited series on Termination Issues for Architects & Engineers (and all Design Professionals).  For the next few weeks, I’ll be posting about all sides of the termination topic, including:

Part 2:  How to handle construction administration when the contractor is getting fired

Part 3:  How to handle contract administration when the contractor is firing the owner

Part 4:  What to do when they want to fire you, the architect or engineer

Part 5:  What if You are the one that wants to quit?

and finally:

Part 6:  This is the End (Construction Contract Termination quick facts for the design professional)

Stay tuned for the next several weeks to learn all you ever wanted to know about termination, resignation, and the breaking of contracts.

In the meantime, if you have any burning termination-specific questions or comments, drop them in the comments below.  See you soon!


Photo By Leon Schlesinger Productions, produced for Warner Brothers. – YouTube screen capture; Public Domain,

Incorporation by Reference in your Design Services Contract– what does this mean, and are you at risk? (law note)

Has an Owner ever asked you to sign his contract before you started work on a new design project?  Rhetorical question– this happens all the time, right?  Especially in commercial work, developers or owners typically are not happy to simply agree to your Proposal for Services, but instead want you to sign *their* contract.

No to dogs drinking and smoking on skateboard

Make sure you know the risks you are taking on- or just say no!  (Sign in a cafe showing a smoking, drinking, skateboarding dog)

There are some risks with that you should be aware of — one of which is the seemingly arcane and legalistic language that reads something like this:

“The Developer’s contract with Owner is hereby incorporated by reference.”

What does this mean?  This language means that you have legal responsibilities that you may not even be aware of.  If the Developer agreed with the Owner to a certain a time frame (i.e., a  “time is of the essence” clause), or any particular performance standard (LEED certification, for example), then you also have agreed to these terms.  Did you know that?

So many times when I’m asked to review a contract for an architect, there is language incorporating a document that they never have even seen.  NEVER sign any such contract until you have gotten the document “incorporated by reference”, viewed it with your risk managers, insurance broker, and lawyer, and made the decision that you can live with those terms.

Clauses that are incorporated *are* legally enforceable.  Make sure you know what you are getting into.

Hat tip to Colleen Palmer at Beazley A/E whose Managing Risk video on this topic inspired today’s post.

What about you?  Have you asked for all documents you are agreeing to, before executing on a contract?  If not, start doing so today.

Photo (c) Melissa Brumback.  Creative Commons License