Contract Change #8: Direct Communications between Owners and Contractors (law note)

talking headsContinuing our 10 part series on Changes to the General Conditions of the Contract (AIA 201) [for the previous post, click here], Change #8 has to do with direct communications between the Owner and the Contractor.

As the Engineer or Architect of Record, you probably have frequently experienced Owners and Contractors communicating directly, in direct contravention of the language of the contract that requires them to endeavor to route all communications through the design team.  With the latest version of the 201, direct communication is now authorized, to recognize both the reality of what was happening on the ground and to recognize that sometimes Owners and Contractors may need to communicate without waiting for the design team.

In the new Section 4.2.4, Owners & Contractors are only required to include the Architect in communications that relate to the professional services of the design team.  HOWEVER, the Owner is required to promptly notify the Architect of the substance of any such direct communication.  The Owner-Architect agreement has been changed as well, to make it consistent with this new AIA 201 procedure.

Is this a good change?  Honestly, the verdict is out on that one (pun intended).  It may prove very helpful in keeping a project on track when the Architect is not regularly on-site.  However, the parties run the risk that they may make decisions that do effect the design team, without design team input.  Be cautious, and make sure the Owner *does* keep you informed.

Up tomorrow, Change #7– Contractor’s Means & Methods.

Contract Change #9: Owner’s Right to Carry Out the Work (law note)

construction workerChange # 9 to the AIA A201 General Conditions has to deal with the Owner’s Right to Carry Out the Work.  [Click here for the previous post on AIA Contract Changes.]

In prior versions of the General Conditions, if a contractor defaulted and the Owner (after giving notice) opted to cure by carrying out the work itself, an appropriate Change Order would be issued.  However, a Change Order is a contract that requires an agreement by both the Owner and Contractor, and, obviously, Contractors were reluctant to agree that they were in default and responsible for a deductive change order.

The new Section 2.5 allows the Owner to carry out the work if the Architect approves, without a signed change order.  Instead, the Architect can withhold or nullify a payment to the Contractor (under Section 9.5.1) to reimburse the Owner for the work carried out.

If the Contractor disagrees with the actions of the Owner or the Architect, or the amounts claimed as costs to the Owner, the Contractor can institute a Claim under the Claims section (Article 15) of the 201.

Up tomorrow, Change #8– Direct Communications on the Construction Project.

Contract Change # 10:   Differing Site Conditions (law note)

mud slide site conditionsAs promised in my note yesterday, today begins the first in a 10 part series on the most significant changes to the AIA A201, General Conditions to the Contract.

I’ll take the changes in reverse order, a la David Letterman…..

Change #10:  Differing Site Conditions

Previously, the A201 required a Contractor to provide notice to the Owner and Architect within 21 days after discovery of unforeseen site conditions.  This notification is required prior to the conditions being disturbed, so as to allow the Design Team the ability to evaluate the site and determine the compensability of any such differing conditions.

The requirement has been shortened to 14 days — that is, under the 2017 version, a Contractor must give the notification within 14 days of discovery.   See Section 3.7.4.

This is a small contract adjustment, but could prove substantially deprive a contractor of potential additional sums if caught unawares.  As the Architect or Engineer of Record, you should also be aware of this new 14 day requirement, which is a week shorter than most AIA deadlines.

Stay tuned for Change # 9, dealing with the Owner’s Right to Carry Out the Work, in the next post.

 

Photo courtesy NPS.

 

Like Death and Taxes, AIA Contract Changes are a Sure Thing! (law note)

AIA Contract ChangesLike death & taxes, you can count on the American Institute of Architects (AIA) to regularly update their standard form construction contracts.  Most such forms are updated every 10 years, and 2017 was no exception.

In the 2017 version, the changes are “evolutionary, not revolutionary”, according to AIA Managing Director and Counsel, Kenneth W. Cobleigh.  Ken and I both recently spoke at the North Carolina Bar Association’s Construction Law Forum on various AIA changes.

Over the course of the next two weeks, I’ll be presenting a 10 Part Series on the Top 10 Changes that you need to know about the AIA A201 General Conditions.

Stay tuned for Part 1, on Differing Site Conditions, which will be posted tomorrow morning.

 

Picture adapted from Investment Zen, with thanks.

Consequential Damages: What are they? Should I waive them? (law note)

A client asked me about a contract he was asked to sign in which consequential damages were being waived.  Consequential damages are those things that cost money which arise indirectly out of a failure of a party on a construction project.   dollar signsThey can include:

  • loss of use
  • loss of rent
  • loss of profit
  • loss of bonding capacity
  • extended overhead
  • extended equipment rental fees
  • increased material costs
  • interest

Note that this is not an exhaustive list, and other consequential damages may be applicable depending on the project.

Often, like my client, you may be asked to waive consequential damages.  This is a double edged sword.  If the waiver is mutual (something on which you should insist), then the provision may save you money in the event your design or services delay the project.  The Owner has agreed that it cannot seek to recover indirect, consequential damages.  On the other hand, if you are the one suing the Owner, it means that there may be costs that you cannot be compensated for if a project goes awry.

The standard industry contracts all have at least some waiver of consequential damages, as noted in this chart.

waiver in form contractsBottom line: waiver of consequentials can be a good thing or a bad thing, but you will not know which when you are signing on the dotted line.

Just make sure that if there is a waiver, that it is mutual on both sides.  Good luck, and “be safe out there

Your turn.  Have you ever waived your right to consequentials?  Horror story to share about paying someone else’s costs?  Share in the comment section.

Dollar Photo (c) sivlen001.
Chart (c) Melissa Brumback Creative Commons License