Construction, er make that CONTRACT, Administration services: a primer (law note)

[Update 12:42 pm ET, 11/3/11– CA is for Construction Contract Administration, or “Contract Administration” for short- thanks Liz O’Sullivan]

 One of the Architect’s responsibilities on a construction project is that of construction contract administration (“CA”).  While not every contract contemplates the architect performing a CA role, most commercial construction projects do.  What, exactly, should be included in the CA role?  The CA role can be whatever the parties agree upon.  In fact, the AIA A201 form contract documents anticipate that the architect’s role will be defined in an exhibit. 

Construction Construction Contract Administration
§ 4.2.10 If the Owner and Architect agree, the Architect will provide one or more project representatives to assist in carrying out the Architect’s responsibilities at the site. The duties, responsibilities and limitations of authority of such project representatives shall be as set forth in an exhibit to be incorporated in the Contract Documents.
What, then, should be included in the CA role assigned to the architect?  The nature of the construction administration role is project specific.  Some projects require a full-time on-site architect, a clerk of the works, or a weekly or bi-weekly site visit.  Because the nature of the CA role cannot be adequately described in a form document, it is especially critical that you take care to describe the specific CA duties assigned to the architectural team in detail.
site observation by architect
 
One of the main CA roles for the design team is that of site observation. Consider:
  • What frequency is contemplated for visits?
  • How long should those visits last? 
  • What is your role during such site visits?
I see many disputes that arise over a misunderstanding as to how often the architect should be on-site, and what his role is in observing the contractor’s work once he is there.  Again, being specific will only help you to avoid misunderstandings, possible litigation, or even extra liability later on.
 
Perhaps the most important concept to remember for your CA role on a construction project: never agree to “inspect” the contractor’s work.  Your role should be observation to see that the work is in general conformance with your design.  You cannot guarantee the contractor’s work (nor would such be insurable).  Therefore, be careful to use the word “observation” and not the word “inspect” in your CA description.
 
What have been your construction observation experiences? Drop me a line and tell me your story.  (And thanks to my many new readers to the blog this week!).
 
 
 
 Photo (c) Mark Hogan via CC.
 
 

 

Planning Ahead for Additional Compensation

money for additional services for construction administration

Does your designer contract have provisions in it for additional compensation in the event the construction project takes longer than the parties anticipate?  If you use the AIA 201 (2007) general conditions for the Contractor, it may.  The AIA provisions include:

 

 § 1.1.2 THE CONTRACT

The Contract Documents form the Contract for Construction. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations or agreements, either written or oral. The Contract may be amended or modified only by a Modification. The Contract Documents shall not be construed to create a contractual relationship of any kind (1) between the Contractor and the Architect or the Architect’s consultants, (2) between the Owner and a Subcontractor or a Sub-subcontractor, (3) between the Owner and the Architect or the Architect’s consultants or (4) between any persons or entities other than the Owner and the Contractor. The Architect shall, however, be entitled to performance and enforcement of obligations under the Contract intended to facilitate performance of the Architect’s duties.

The language that I bolded is very important language.  It may provide a mechanism to recoup additional service fees for extended construction administration services.  Note, however, that I said “may.”

If your fees are based on a set number of construction days, what happens if the project gets extended?  Do you simply go without pay for extra months of CA services?  Do you re-negotiate with the Owner at that time?   You should consider this issue in advance to avoid disputes later on. 

Best practice?  A clause in the Owner-Designer contract that states that additional services compensation will kick in after a certain date,  at a set value per month.  

If you wait until the issue comes up during the final phase of construction, you have much less bargaining power.  You also run the risk of the Owner claiming errors and omissions against you when you present a bill for extra services.  Deal with the issue up front, in much the same way that unit prices for rock overages are provided for upfront in the contractor’s contract. 

Do you have experience with getting additional compensation after construction delays?  What worked best for your company?  Share below. 

And, sign up for email delivery of blog posts to your mailbox!

 Photo (c) Freefoto.com via Creative Commons license.

 

Handling Threats of Contract Termination in the Construction Context

The threat of a contract termination, especially one “for cause” as opposed to “for convenience” , is something that strikes terror in the heart of many contractors.  The request by an owner to terminate for cause is something that must be handled carefully by the design professional/contract administrator.  A misstep by any party can cost untoward damages relating to contract termination in the construction context.