Joint & Several Liability in NC (law note)

British pennies & poundsIf a client has been sued, he wants to know how much is at risk if he loses at trial.  This is especially true where more than one person or company have been sued.  How is any damage award apportioned?

 The answer is not one clients generally like to hear:  your company can be on the hook for 100% of any damages.  This is true even if your company is really only liable for a tiny fraction of what caused the damages in the first place.  You can thank “joint and several liability” for that.

—————————-

For example, in a fairly typical construction dispute, an owner sues a contractor and the architect for construction defects. The contractor uses unsuitable substitutions, and the architect approves the unsuitable substitutes.   Both contractor and architect may be held liable for the resulting damages.  If a jury awards the owner $500,000, then both contractor and architect are liable for the entire $500,000 to owner.  That’s the “severability” part of the law.  As between the two, of course, they both share in the damages, and if the owner executes on the entire judgment against the architect (perhaps due to the architect’s insurance coverage), the architect can then go after the contractor for an equal share and get paid back $250,000 in “contribution.”  (That’s the “joint” nature of such an award).  This is, however, assuming the contractor has those funds.  Essentially, whoever has the funds when a judgment hits might end up paying for the entire award.  If the contractor doesn’t have $250,000 for the architect to be paid back, the architect is out of luck.

Does the result change if the jury finds the architect was only 5% liable for the damages and 95% were attributed to the contractor? Nope.  In North Carolina, where the parties’ actions together contribute to one indivisible injury, there is no apportionment.  “In for a penny, in for a pound” as the old saying goes.

Exceptions to the Rule?

Are there exceptions? But of course!  If the owner is also negligent, he can get no recovery at all since North Carolina is a pure contributory negligence state.  If one party is actively negligent and one passive, than the passively negligent party can seek indemnity from the active party.  If one party settles before trial, things become more complicated.  More on these subjects in future posts.  I’m also told that in other states apportionment is more the rule, so you may have better luck with your out of state projects in a similar situation.

As a general rule of thumb, however, for your North Carolina project, just assume that the entire amount of claimed damages may be presented to you for payment.  Unfair? Many times, yes.   That’s the nature of the beast.  It is also one of many, many good reasons to make sure you are doing business with people you trust and, more importantly, that other professionals are appropriately insured or bonded on any project you are working on.

If you have any questions about joint and several liability, drop me a line or a comment below.

 ______________________

Photo “Shiny pennies” by David Pillbro (Flickr Creative Commons license)

 

Tolling the Statutes of Limitation & Repose? (Law note)

Lowe's Motor Speedway

A blog reader recently raised the question of to how to handle construction defect claims while repair attempts are being made on a defective building.  In part, the answer to this question will depend on how close you are to the statute of limitations or the statue of repose from running.  The closer you are, the more you need to be concerned about this issue.  Just because all parties are working together to solve construction issues does not mean that the statutes are not running.  They can.  [There are, as usual, exceptions for equitable reasons.]  And once statues run, there’s no getting them back.

One prudent approach to dealing with the statutes is to have all parties involved enter into a “Tolling Agreement.”  What a properly drafted tolling agreement can do is to stop the running of the statue of limitations and/or repose while the parties attempt to fix the defects or otherwise settle their issues with one another.  Note that the tolling agreement does not give a party any greater rights than they would have at the time it is signed– that is, if the statute has *already* run, then it would be of no use.  But the tolling agreement can act as a “time out” on the running of the clock.

A good example of a tolling agreements is found in the Court of Appeals opinion in Charlotte Motor Speedway, Inc. v. Tindall Corporation, 195 N.C. App. 296, 672 S.E.2d 691 (2009).  The Speedway case involved the infamous collapse of a pedestrian walkway during the NASCAR Winston Cup.  The walkway which collapsed had been substantially completed by October 1995, and the collapse occurred in May 2000.  Speedway (the project owner) and Tindall (which constructed the walkway) entered into a tolling agreement:

“to toll and suspend any applicable statute of limitations, repose or time, whether created by statute, contract, laches or otherwise, within which any cause, claim action, cause of action, or suit must be made, or commenced by the parties against any one of them concerning the [pedestrian] claims, including any and all claims for indemnification and contribution.”  Id. at 298, 672 S.E.2d at 693.

Tindall attempted to argue that the statute of limitations barred Speedway’s claim for indemnification of monies paid prior to three years before it filed its complaint, but the Court found that the Tolling Agreement, which remained effective “through and including January 1, 2006” tolled the action, and Speedway brought suit on July 17, 2007, less than two years after the Tolling Agreement expired.  Likewise, the Court held that the statute of repose did not bar the action, because the Tolling Agreement was entered into less than six years after substantial completion, and the lawsuit was brought during the pendency of a second funding [tolling] agreement between the parties.

If you are considering a tolling agreement (or think you don’t need one because you “have time”), it is always smart to get a professional opinion on the matter.

______________________________

Comments? Let me know.  I welcome the opportunity to discuss how the statute of limitations and repose may be tolled in your specific situation.

______________________________

Photo “Trucks” by JMLeedy (Justin Leedy) via Flickr via Creative Commons License.

 

Follow your Change Order Requirements

 check markIt is extremely important that you follow your written contract requirements.  No where is this more evident than in the change order process.

Most contracts have an explicit provision for the payment for additional work– and they generally require a written, signed change order (or change directive) before the work is performed.  Can you get by with verbal agreements for additional work? Sometimes yes, sometimes no.  Will it be much harder to get paid for additional services without a signed change order? You bet.  So why put yourself through that trouble?

Often times parties begin to “waive” formal requirements for written change orders, and construction projects are often on tight deadlines where stopping work to get a fully executed change order would bog down the schedule.  However, you run the risk of throwing yourself on the mercy of the Court when you don’t play by the contract rules.

A new case out of the Eastern District of Virginia demonstrates this fact very clearly.  In Artistic Stone v. Safeco, 2010 WL 2977894 (E.D.Va July 27, 2010), the Court held that the requirement that change orders be in writing was to be strictly construed and the subcontractor in that case could not recover for verbal change orders that violated the written change order requirement.  The Court held that where there is a method to ensure recovery of additional extra work in the written contract, the subcontractor could not recover additional money when it failed to follow that method.

“Written change order requirements maintain order and predictability in the construction business, and are meant ‘to avoid subsequent disagreement, and prevent just such a controversy as has arisen in this case.  For this reason, ‘where there is a method under the contract by which a party can insure the recovery of the cost of extra work, that party is not entitled to recovery where it fails to follow that method.'” Artistic Stone Crafters at 5.   [Internal citations omitted.]

A North Carolina court would likely concur.

To ensure you can fully recover for extra work, make sure it is authorized.  Follow the contract.  If circumstances make it so you cannot always follow the contract terms, document the situation as best as you can.  A follow-up email, confirming a verbal change order, would at least provide written evidence you can present in Court, should it come to that.  Otherwise, arguments can and will be made that the person who gave the change order wasn’t authorized to do so, and you may be stuck with no recovery for the extra work.

_______________________

Photo “white check mark on blue- acrylic on canvas” by kylemac via Flickr via Creative Commons license.

Exception to the Statute of Repose?

Hold the phone– didn’t I just say last week that the statute of repose was basically an absolute bar to any action after 6 years?  Why, yes, yes I did.

BUT it too has exceptions!  (If you’ve learned anything from my rantings, I hope it is that there is always an exception to the rule).  In a recent Court of Appeals case, the application of the statute of repose was called into question.

In Dawson v. N.C. Dept of Environment and Natural Resources (June 15, 2010), a couple bought land only after inquiring of the Person County health department to determine that the lots perked.  Based on a 1989 letter issued by the health department stating that the lots perked, the couple bought the land.  In 2000 (that is, 11 years later!), the couple applied for building permits only to learn from DENR that the land was not suitable for building.

The couple sued DENR under a negligence theory, and DENR argued the time bar of the 6 year statute of repose.  In its decision, the court held that because the 1989 letter was not based on an improvement to real property, the statute of repose was not applicable.  The Court indicated that, had the county inspector been inspecting an existing septic system, their decision may have been different.

Moral of the story? Just because you think you have a good defense, don’t forget that there is always an exception to the rule or, rather, there are many times when the shoe looks like it fits, but it really doesn’t.  Be careful– blisters are painful!

boot

Photo “Dakota Composite Dual Toe” by Bottinex via Flickr via Creative Commons Attribution-Noncommercial-Sharealike license 

Statute of Repose: Putting your Risk to Bed

Ferret's new hammock

Last week, I discussed the statute of limitations  and how it is generally applied to North Carolina construction projects.  Today, I want to introduce you to another important concept: the statute of repose.

What is the Statute of Repose?

The Statute of Repose is another time-barring statute within which your claim must fit. Like the statute of limitations, it depends on what state’s law will apply to your case, which is usually, but not always, the state where the project is located.

The Statute of Repose, under N.C. Gen. Stat. §1-50(a)(5)(a) provides:

“No action to recover damages based upon or arising out of the defective or unsafe conditions of an improvement to real property shall be brought more than six years from the later of the specific last act or omission of the defendant giving rise to the cause of action or substantial completion of the improvement.”

When does it run for North Carolina construction projects?

The Statute of Repose in North Carolina for improvements to real property is currently six (6) years from substantial completion or the last specific act or omission of  the defendant, whichever is later. N.C. Gen. Stat. §1-50(a)(5)(a); Nolan v. Paramount Homes, Inc., 135 N.C. App 73, 518 S.E.2d 789 (1999).  Once you have been off of a job for 6 years, you cannot (successfully) be sued for any construction defect, regardless of when the defect was or is discovered.  It is an extreme, bright line bar to any claim after that time; that is, it puts your risk to bed.

How is it different from the Statute of Limitations?

Unlike the Statute of Limitations, the Statute of Repose starts running whether or not you are aware of any defect.  Bryant v. Don Galloway Homes, Inc.,, 147 N.C. App. 655, 556 S.E.2d 597 (2001). This is a double-edged sword—if you are the one whose work is being questioned, you can rest easy that after you have been off of a project for 6 years, no claim can thereafter be (successfully) brought against you.

On the other hand, you are also bound by the repose statute, regardless of any equitable considerations. For example, in Monson v. Paramount Homes, Inc., homeowners sued a general contractor for defective construction, and the contractor brought a third-party action against his subcontractor. The claims against the subcontractor were deemed time-barred under the statute of repose.  133 N.C. App. 235,515 S.E.2d 445 (1999). In Monson, the contractor had to defend the action but had no ability to recover from the subcontractor who actually performed the poor construction.

Does punch list or warranty work extend the Statute of Repose?

In most cases, no.  Once the statute of repose starts to run, it generally cannot be tolled by any subsequent action.  For example, in one case, even when the contractor had performed some punch list work after substantial completion, and even though the architect failed to issue a certificate of substantial completion, the court held that the statute began to run at the date of substantial completion of the contractor’s work.  Mitchell v. Mitchell’s Formal Wear, Inc, 168 N.C. App, 212, 606 S.E.2d 704 (2005).

This is also true if you return to the job for minor warranty type issues during the 6 year period. The statute of limitations is tolled during the repair time, but in general, the statute of repose is not tolled once it begins running. The policy behind this interpretation is that the Statute of Repose is a substantive right designed to limit the potential liability for a set period of time.

 ___________________________

Photo “Cama nova do furas / Ferret’s new hammock” by Isa Costa via Flickr via Attribution-NoDerivs 2.0 Generic Creative Commons license.