NC State Construction projects– Privity, Multi-Prime Contracts, and the Ability to Be Sued by Parties You Don’t know (Law note)

At the recent seminar on construction law in North Carolina, I was asked whether parties could be sued by other parties on state construction projects when there is no contract between those parties.  The answer is yes. In the following series of blog posts, I will address three major cases which address this question in several different permutations.

For today’s post, I will discuss contractual privity, the multi-prime statute, and how the two apply on North Carolina state construction projects.  In later posts, I will discuss the application of that statute to different parties in the construction context.

Multi-prime contracts

In North Carolina, the state entity who is the owner of the construction project must bid the project pursuant to one of several designated ways.  One common method sometimes required of public bidding is the “mulit-prime” contract, in which the State has at least 4 separate contracts, for:

(1) Heating, ventilating, and air conditioning

(2) Plumbing and gas fittings

(3) Electrical wiring and installations

(4) General construction relating to erection, alteration, or repair on public property

N.C. Gen. Stat. §143-128(a). 

The purpose of the multi-prime statute is two-fold:

  1.  It encourages lower bids by preventing pass-through cost mark-ups to the state
  2. It allows smaller specialty contractors to enter bidding directly with state without having to have a working relationship with a general contractor, thereby opening up state jobs to a wider array of potential contractors
Contractual Privity

 In general, contractual privity is required to sue another entity on a construction project—that is, you have to be in a contractual relationship with the party you are suing.  There are exceptions to this rule.  For example, you can be sued in negligence for property and personal damage by a party that you do not have a contract with.  (See my post discussing the architect’s liability for economic loss  resulting from breach of architect’s common-law duty of due care  ).  In addition, the state legislature has provided the ability for contractors to sue one another, or other entities involved in the construction project, without having to sue the owner or deal with the State Construction Office.

 NC statute on liability:

Each separate contractor shall be directly liable to the State of North Carolina, or to the county, municipality, or other public body and to the other separate contractors for the full performance of all duties and obligations due respectively under the terms of the separate contracts and in accordance with the plans and specifications, which shall specifically set forth the duties and obligations of each separate contractor. For the purpose of this section, “separate contractor” means any person, firm or corporation who shall enter into a contract with the State, or with any county, municipality, or other public entity to erect, construct, alter or repair any building or buildings, or parts of any building or buildings.

N.C. Gen. Stat. §143-128(b).   [Emphasis added].

This statute has been interpreted over the past decade to allow essentially any party to sue any other party directly on state construction projects.  In the next blog post, I will discuss the first of three major cases dealing with this issue.

Green Design | Legal risks to designing a Construction project for LEED certification (take 2)

As I noted in an earlier post about risks related to designing buildings for LEED certification, those involved in construction should proceed cautiously in designing to certain LEED standards.

A recent Insurance Journal article discusses insurance and liability risks for a designer or contractor if he guarantees a certain level of “green” performance in his construction contract.

“If you’re an architect, engineer, or contractor, and you’re guaranteeing to your client that the building will be Gold certified by the U.S. Green Building Council, you’re opening up a pretty big can of worms.”

You should never “guarantee” any performance to keep your risks minimized, your insurance in place, and your attorney happy. This article is another reminder to be especially cautious in green construction, and to not make promises that you may not be able to keep.

ConsensusDOCS- are they an improvement over AIA construction contracts?

Have you had occasion to use the (relatively) new ConsensusDOCS? Having just completed my manuscript for the North Carolina Construction Law seminar I’m speaking at in May, I’ve been spending a lot of time comparing the American Institute of Architect’s standard contract general conditions, the AIA A201 (2007) to the ConsensusDOCS 200 (2007) and the Engineering Joint Contracts Document Committee (EJCDC) standard general conditions of the contract, C-700 (2007).

I haven’t yet seen litigation over the ConsensusDOCS, so how courts will interpret its provisions remains to be seen. One major difference: the ConsensusDOCS do diminish some of the architect/design professional’s role on the project.

For example, in the change order process, instead of the architect being involved in the contract price and time adjustment (see AIA A201 Section 7.2.1), the ConsensusDOCS 200 calls for the owner and contractor to negotiate in good faith. No mention is made of the design professional’s role. (See 8.1.2).

If you’ve had occasion to work under the ConsensusDOCS, drop me a line and tell me the advantages and disadvantages over other form contracts.

NC Construction Law Seminar in Greensboro

Excuse the little self-promotion here, but if you want a quick way to learn more about construction issues in North Carolina, I’m speaking at a seminar on May 7, 2010 in Greensboro, NC.

The seminar topics include:
* Understanding Liens, Bonds, and Payment Issues
* Risk Transfer (including insurance and indemnity issues)
* Making Changes & Resolving Disputes during the Construction Process
* Contracts and Subcontracts on Public Projects
* Recent Bankruptcy Cases Impacting Contractors’ Lien Rights

The seminar qualifies for 6.0 PDHs for NC Engineers, 0.6 CSI CEUs, and NC Attorney CLE credit is pending.

Joining me in speaking are Eric Biesecker, Jennifer Maldonado, and Brian Edlin. For more details or to register, go to Half Moon Seminars.

Female architects- Project focuses on industry pioneers

While architects these days come in either gender, it used to be rare for an architect to be female. As noted in today’s Durham Herald, George Smart, the founder and director of Triangle Modernist Houses, is working to profile female architects who broke new ground.

According to TMH, women now make up about 20% of the architectural field vs. only 1.2% from the 1940s through the 1970s.

More information on the project is found on the Project’s website.