Renewables & Incentives Database (Tue Tip)

Isun and cloudsnterested in knowing what state incentives may be applicable for your energy efficient construction project?  Check out the Database of State Incentives for Renewables & Efficiency (DSIRE). 

The searchable database provides a comprehensive source of information on state, local, utility and federal incentives and policies that promote renewable energy and energy efficiency.

Do you have a “hot” link to share?  Let me know!  And, sign up for email delivery of all blog posts right to your in-box so you’ll never miss a post!

———————–

Photo (c) Joshua Sosrosaputro via Creative Commons license.

You Cannot Have Your Cake and Eat It, Too! (Estoppel) (law note)

slice of chocolate cake We’ve talked previously about the statute of limitations  here at Construction Law in North Carolina.  A recent North Carolina Court of Appeals case gives a vivid example of one exception to a statute of limitations defense– estoppel. Estoppel is the act of lulling a party into not filing a lawsuit through your actions.  You are then deemed “estopped” from asserting the statute of limitations as a defense. That is, a party cannot use the statute of limitations as a sword to benefit from his own conduct which induced a plaintiff to delay filing suit.  Proof of actual fraud or bad faith is not required; however.  The “basic question” is whether defendant’s actions “have lulled the plaintiff into a false sense of security and so induced [the plaintiff[ not to institute suit in the requisite time period.”  Cleveland Const., Inc. v. Ellis-Don Const., Inc. et al., __ N.C. App. __, 709 S.E.2d 512 (5 April 2011). In that case, the general contractor on a public hospital project, Ellis-Don, asked Cleveland Construction Inc. (CCI), one of its subcontractors, to delay making its own delay claim on the project.  The general contractor sent a letter to CCI  asking it not to sue it in order to present a “unified front” to the State during the State Construction Office’s administrative claims process. The Court found that Ellis-Don affirmatively represented to CCI that it was  pursuing CCI’s claims as part of its overall claim against the State. The Court further found that Ellis-Don affirmatively represented to CCI that CCI should not  initiate a claim because that would jeopardize the success of the total contractor recovery with the State.  As such, Ellis-Don lulled CCI into a false sense of security, as CCI reasonably believed that Ellis-Don would pass through to CCI any proceeds attributable to its claim from Ellis-Don’s settlement with the state.  Ellis-Don was, therefore, equitably estopped from asserting the statute of limitations when CCI later sued Ellis-Don on those same claims.   Here, Ellis-Don tried to benefit from including CCI’s claim in its overall claim at the State Construction Office, and later benefit from CCI’s failure to adhere to the time limits imposed on bringing claims.  The Court held that a contractor cannot have its cake and eat it too.  (After all, too much cake is bad for anyone). Practice Note:  Do not count on the theory of equitable estoppel for untimely claims.  A court could decide you were not reasonable in holding back from initiating legal action, in which case your claim would be denied.   Equitable theories are to prevent injustice, but you cannot and should not rely on them.  Have you ever delayed filing suit on the promises or statements of another party?  Did the Court find the other party was equitably estopped from claiming a statute of limitations defense, or did the Court allow such a claim?  Share your experience in the comments section below.

———————–

Photo:  (c) Dennis Mojado via Creative Commons license.

Why Misery Loves Company (aka Concurrent delay on the Construction Project) (law note)

You know the old saying, “Misery loves company?”  It’s true.  Even in the construction world.

misery license tag

What happens if, while the design team is asleep at the switch, the contractor is also delaying the project, or the owner is dithering about a materials selection?  Since there was more than one cause of the project delay, does that let you off the hook?  Maybe so.

The above scenario is, in its bare-bones basics, an example of concurrent delay.

What is concurrent delay?  Concurrent delay is delay to the critical path of construction, caused at the same time by multiple events not exclusively within the control of one party.  In other words, it is when two or more parties both contribute to the delay of the project.

In such a case, neither may recover damage from each other, unless there is proof of clear apportionment of the delay and expenses.  See Biemann & Rowell Co. v. Donohoe Cos.,147 N.C. App. 239, 245, 556 S.E.2d 1, 5 (2001).

Where both parties contribute to the delay, neither can recover damages, unless there is proof of clear apportionment of the delay and the expense attributable to each party.  In such an instance, the only remedy for both parties may be an extension of time to the contract.

Have you experienced a case where concurrent delays existed on a Project?  Were you able to apportion the delay damages, or did all the culpable parties pay the price?  Share below. 

Also, please sign up for email delivery of blog posts directly to your inbox!

—————————————

Photo: Misery by Molly Helzschlag via Creative Commons license.

Should You Be a LEED Green Associate? (Tue Tip)

LEED Green Associate

Those of you who follow my twitter stream know that I recently passed the exam to become accredited as a LEED Green Associate.  The LEED Green Associate is a new credential, and the first level of credentialing that also includes the LEED-Accredited Professional + Specialty.

Why did I do it?  I wanted to have a better understanding of the various LEED requirements and sustainability issues when working with my architect and engineering clients.  Many of my A/E clients are AP certified — most before the new burdensomedetailed requirements were issued (not that I’m bitter or anything!).   I, on the other hand, knew just enough about green design to be dangerous.

While I’m ready not exactly ready to go out and leap tall (green) buildings (no doubt complete with vegetated roof) in a single bound, I do have a much broader understanding of the intricacies of complying with not just Code issues but also LEED issues in mind.

So, to return to the title, should YOU get a LEED Green Associate accreditation?  Yes.  If you are reading here, then you probably would benefit.  (Unless you StumbleUpon’d your way here, in which case, not necessarily!)  If you work with architects and engineers, and certainly if you are an A/E and haven’t yet gotten green credentialing, get your Green Associate credential.   You will learn about a wide cross-section of green issues, including sustainable sites (SS), water efficiency (WE), energy & atmosphere (EA), materials & resources (MR), indoor environmental quality (EQ), innovation in design (ID), and regional priority issues.

Are you interested in becoming a Green Associate?  Let me know and I can share some study tips. 

Or, are you already accredited with the USGBC?  Under the old or new system?  What has it taught you?  Share in the comment section below.

  ———————–

“LEED Green Associate” and the LEED Green Associate logo are trademarks owned by the U.S. Green Building Council and are awarded to individuals under license by the Green Building Certification Institute.