Expect the Unexpected (your design contracts in a post-COVID world)

Have you adapted your post-COVID practice to better plan for the “unexpected” ?  In particular, have you looked at–and revised– your professional services contracts to give yourself a little more breathing room for unaccounted issues that may arise?  If not, no time like the present.

Don’t like that saying?  How about ” a stitch in time saves nine?”  No?  Still nothing?  What about a picture of something so completely unexpected it shocks you– say, a fireman commuting home, in fire-fighting regalia, on a tricycle?  Okay, here you go…

Fireman-bikerNow that I have your attention– you should make it a practice to regularly review and update your professional services agreements, and you should consider issues such as:

  1.  Does your agreement provide for extra compensation if you have to spend more time or a longer period providing construction administration services for material delays or labor shortages?  If not, it should.
  2. Does your agreement have a well-written “act of God” provision– one that includes pandemic/epidemics as part of the “act of God” conditions in which a term may become void?  If not, add it now!
  3. Have you considered whether you want arbitration instead of litigation if a lawsuit does arise?  And if you want to arbitrate, does your contract give specifics, like how many arbitrators will decide the case?  These things can be added now with little effort, or you can pay your lawyer to negotiate them down the line.  Guess which is cheaper?

You *do* have a good, solid contract to begin with, correct?  If not, I’ve previously given examples of how to craft helpful scopes of services and how to add the protection of a well-crafted exclusion to your scope of services.   Check them out, and be ready for the next biker-fireman surprise in your future.

Photo (c) MelissaBrumbackCreative Commons License

Are we having fun yet? Construction in a post-COVID world (law note)

Remember how I said to never assume?  Yeah, about that……   even when you plan for failures, mistakes, and other problems, sometimes things get so outside the realm of what you considered that it can leave your construction project spinning.  Take, as a random example, a world-wide pandemic that shuts down supply chains, shuts down job sites, and limits the labor pool.  Just as an example.

What does construction law say about pandemics?  They fall under an “Act of God” that you may have read about in your contracts, or in the contracts of the contractors working your projects.  An “Act of God” is an event that is not foreseeable, and as such not something the parties could have anticipated when they drafted the contract.  Acts of God generally excuse a party’s failure– for example, a contractor’s failure to complete the project on time can be excused when an “act of God” has occurred. 

By now, you’ve dealt with the practical fall out, one way or another.  Many projects no longer made financial sense for your clients.  Others may have been modified, reduced in scope, or had substitute materials put in place.

What do you, as an architect or engineer, do now, faced with the potential for further shut downs, supply chain issues, and other COVID variants?  The short answer is to give yourself options and assume changes will be needed to your own scope of work on each project.  Consider:

  1.  If the project needs to be re-designed to account for shortages, can that be an additional service that you get paid for?
  2. If the project requires substitute products, how many of those are part of your basic service, or is there a point at which you should get paid hourly for researching, reviewing, and approving substitutes?
  3. If the project takes a lot longer than anticipated to complete, whether due to government shut downs, labor issues, or supply chain problems– can you get paid increased contract administration fees?  And, is there a contract provision that allows you to increase your hourly rate after X number of months, to reflect inflation?

These are some of the ways that you, as a designer, can protect yourselves from ongoing delays, and make sure you are not tied to a project without a way to recoup your extra costs.

Thoughts?  Questions?   Share what’s worked for you or what you’d like to learn more about in the comment section below.

 

 

Will Green Performance Bonds Be a Surety Requirement in 2012? (law note; guest post)

Today’s Law Note is by Guest Blogger Alex Levin for JW Surety, the largest surety bond agency in the country.  When he’s not explaining the functionalities of surety bonds, he covers a variety of topics from construction-related news to eco-friendly building tips.

Green building design and construction is an attempt to conserve natural resources, reduce energy consumption, and protect the environment through reduction of pollutants. Green buildings are constructed with renewable, managed materials and are typically designed to take full advantage of natural light and passive heating and cooling environments.

In 2006, the District of Columbia enacted a local ordinance specifically designed to promote green buildings. The Green Building Act of 2006 becomes effective in 2012 and requires all new construction projects within the District to meet Leadership in Energy and Environmental Design, or LEED, certification standards.

Developed by the U.S. Green Building Council, LEED certification promotes the design, construction and operation of green buildings. There are four levels of certification, from LEED Certified to Silver LEED certification to Gold LEED certification and, at the highest level, Platinum LEED certification.

The District of Columbia was the first city in the US to require that privately constructed buildings meet LEED standards and already contains 24 buildings that are certified as Silver LEED or higher. An additional 150 projects are LEED registered.

The Green Building Act of 2006 did several desirable things for the District of Columbia. It established high-performance building standards for all new construction in the District. It created a green building incentives program to rewarded green construction projects with an expedited documents review process. It requires that properties with green building standards be given priority when the District leases buildings. Unfortunately, the Act also had an unintended consequence. As it is currently written, no structures can be constructed in compliance with the Act.

In routine construction contracts, performance bonds limit the risk that owners incur by using a particular contractor. The contractor buys the performance bond from a surety company, and the bond is issued to the project owner. If the contractor fails to perform, the owner can draw on the bond to hire another contractor to complete the project according to the design specifications. When the contractor does complete the project according to the design specifications, the bond is released and money is returned to the contractor. Performance verification is a simple matter of construction observation and comparison with the project specifications.

With a Green Performance Bond, however, there are multiple problems. Performance certification must come from a third party, such as the US Green Building Council, who would not be a participant in the surety bond. A delay on the part of the government agency could result in missed construction deadlines. To add to this, green standards are constantly changing. A project designed to meet Silver LEED certification requirements at the time construction starts may fall short of the certification requirements that are actually in effect by the time construction is completed.

The greatest hurdle to the Act is that Green Performance Bonds simply do not exist today. Surety companies will not issue such bonds when there are no clear standards for performance verification. [Editor’s Note: For more on the “unicorn” that is the green surety bond, check out Chris Cheatham’s discussion on the illusory bond way back in 2009].

The legal ramifications of this dilemma remain unclear. Will contractors who have been awarded construction contracts scheduled for 2012 be subject to liquidated damages if they are unable to bond and fail to start construction? If surety companies do issue Green Performance Bonds, will the bond be forfeit if LEED certification standards change during construction and the project is not Silver LEED certified? Will delays in certification be held against the contractor when projects are otherwise completed? There are no definitive answers to any of these questions.

The language of the Act is being re-examined, and a public hearing is scheduled for mid December. There is no alternative plan in place should the language of the Act remain unchanged and surety companies decline to issue these specialized performance bonds.

Thoughts, comments, or questions?  Post in the comment section, below.

Photo: (c) coolshots blog via Creative Commons license.

You Cannot Have Your Cake and Eat It, Too! (Estoppel) (law note)

slice of chocolate cake We’ve talked previously about the statute of limitations  here at Construction Law in North Carolina.  A recent North Carolina Court of Appeals case gives a vivid example of one exception to a statute of limitations defense– estoppel. Estoppel is the act of lulling a party into not filing a lawsuit through your actions.  You are then deemed “estopped” from asserting the statute of limitations as a defense. That is, a party cannot use the statute of limitations as a sword to benefit from his own conduct which induced a plaintiff to delay filing suit.  Proof of actual fraud or bad faith is not required; however.  The “basic question” is whether defendant’s actions “have lulled the plaintiff into a false sense of security and so induced [the plaintiff[ not to institute suit in the requisite time period.”  Cleveland Const., Inc. v. Ellis-Don Const., Inc. et al., __ N.C. App. __, 709 S.E.2d 512 (5 April 2011). In that case, the general contractor on a public hospital project, Ellis-Don, asked Cleveland Construction Inc. (CCI), one of its subcontractors, to delay making its own delay claim on the project.  The general contractor sent a letter to CCI  asking it not to sue it in order to present a “unified front” to the State during the State Construction Office’s administrative claims process. The Court found that Ellis-Don affirmatively represented to CCI that it was  pursuing CCI’s claims as part of its overall claim against the State. The Court further found that Ellis-Don affirmatively represented to CCI that CCI should not  initiate a claim because that would jeopardize the success of the total contractor recovery with the State.  As such, Ellis-Don lulled CCI into a false sense of security, as CCI reasonably believed that Ellis-Don would pass through to CCI any proceeds attributable to its claim from Ellis-Don’s settlement with the state.  Ellis-Don was, therefore, equitably estopped from asserting the statute of limitations when CCI later sued Ellis-Don on those same claims.   Here, Ellis-Don tried to benefit from including CCI’s claim in its overall claim at the State Construction Office, and later benefit from CCI’s failure to adhere to the time limits imposed on bringing claims.  The Court held that a contractor cannot have its cake and eat it too.  (After all, too much cake is bad for anyone). Practice Note:  Do not count on the theory of equitable estoppel for untimely claims.  A court could decide you were not reasonable in holding back from initiating legal action, in which case your claim would be denied.   Equitable theories are to prevent injustice, but you cannot and should not rely on them.  Have you ever delayed filing suit on the promises or statements of another party?  Did the Court find the other party was equitably estopped from claiming a statute of limitations defense, or did the Court allow such a claim?  Share your experience in the comments section below.

———————–

Photo:  (c) Dennis Mojado via Creative Commons license.

Why Misery Loves Company (aka Concurrent delay on the Construction Project) (law note)

You know the old saying, “Misery loves company?”  It’s true.  Even in the construction world.

misery license tag

What happens if, while the design team is asleep at the switch, the contractor is also delaying the project, or the owner is dithering about a materials selection?  Since there was more than one cause of the project delay, does that let you off the hook?  Maybe so.

The above scenario is, in its bare-bones basics, an example of concurrent delay.

What is concurrent delay?  Concurrent delay is delay to the critical path of construction, caused at the same time by multiple events not exclusively within the control of one party.  In other words, it is when two or more parties both contribute to the delay of the project.

In such a case, neither may recover damage from each other, unless there is proof of clear apportionment of the delay and expenses.  See Biemann & Rowell Co. v. Donohoe Cos.,147 N.C. App. 239, 245, 556 S.E.2d 1, 5 (2001).

Where both parties contribute to the delay, neither can recover damages, unless there is proof of clear apportionment of the delay and the expense attributable to each party.  In such an instance, the only remedy for both parties may be an extension of time to the contract.

Have you experienced a case where concurrent delays existed on a Project?  Were you able to apportion the delay damages, or did all the culpable parties pay the price?  Share below. 

Also, please sign up for email delivery of blog posts directly to your inbox!

—————————————

Photo: Misery by Molly Helzschlag via Creative Commons license.