Pre-holiday reminder: plan for delays (Tues Tip)

colored leafAs the weather (finally) begins to turn to fall, people begin to make plans for fall and winter holidays with family and friends.  While negotiating the ins and outs of whos turn is it to get you for Thanksgiving this year, remember to plan for holiday delays on your construction projects.

Schedules matter.  And yet, vacations, holidays, weather, sickness, and other delays happen.  As I’ve written about previously on this blog, it is important that you prepare for delays in advance & document unanticipated delays

You know you will not have a full crew working 100% between Thanksgiving and Christmas, or between Christmas and the start of the new year.   Neither will your subcontractors.   Plan on it, and accomodate those delays now, ahead of time.

You also need to make temporary arrangements to fill in the gaps during holidays and vacations– both your own absence from the project and that of other trades.    Figure out who should be the contact person in charge in your absence.  Notify everyone who needs to know.  Inquire of your subs, owners, and material suppliers how they are staffing around the holidays.  Advance planning now equals fewer chances for costly delays.

Think of it as an early present to yourself to save yourself from last minute problems!

 ———————————–

Photo “Fall Color, Autumn Colour, New England” by FreeFoto.com via Creative Commons License. 

Should I stay or should I go now? (Court vs. Arbitration)- Updated

gavelShould I stay or should I go now?
If I go there will be trouble
And if I stay it will be double
So come on and let me know!

Are you wondering whether Court or Arbitration should be made a standard part of your construction contracts?  With apologies in advance to The Clash, there is “trouble” to be found in either venue.

Some companies, and their lawyers, insist that American Aribtration Association (AAA) Arbitration is the only way to go.  Others prefer to take their chances in a local state court.  Who is right?  Neither, and both.  As with anything, there is a cost-benefit analysis that you should go through prior to making either a standard part of your construction contract.

Pluses and Minuses of Going to Court

If a dispute is brought in court, there is a standard, fully vetted set of statutes, case law, court rules, and procedures already in place.  A judge, unlike the typical arbitration panel, is generally more willing to consider defenses based on statue, such as the statute of limitations or the statute of repose.  Summary Judgment, in which a judge will (on occasion) grant a judgment for or against  a party without the necessity of the full blown jury trial, is possible.  Such dispositive, procedural rulings are extremely unlikely to be granted by an arbitration panel.

On the other hand, a court trial means a jury verdict.  Unless the parties agree to waive their right to a jury trial, your case will be decided by true laymen who may have never set foot on a construction site before, and who will not understand the RFI, change order, and pay app process.  Terms like “substantial completion,” “critical path,” and “standard of care” will be foreign to them.

I’ve seen some juries get it right, and I’ve seen some get it wrong.  Most jurors take their responsibilities extremely seriously and will try to apply the law as the judge instructs them.  But at the end of the day, you have people unfamiliar with industry standards determining your case.

Pluses and Minuses of Arbitration

Many standard construction contracts contain arbitration provisions, generally AAA Arbitration.  The typical arbitration includes a three member panel of experts (construction professionals, designers, construction attorneys) who hear the evidence and make a ruling.  That ruling has the full force of law.The reasoning behind such arbitration clauses is that industry professionals better understand the construction process, standards of care, and interrelationships on a complex construction project.  Theoretically, therefore, they are better able to determine the true root cause of damages or delay.

Arbitration is sometimes considered to be less expensive and less time consuming than a court trial.  The arbitration panel generally sets fairly loose procedural and evidentiary boundaries, and tends to allow into evidence things that might not meet the strict Rules of Evidence that a court would apply.  Some of these generalities, however, have not proven to be true in practice.  AAA Arbitration can be costly– the filing of a claim alone is costlier than typical court fees.  Case managers add a layer of bureaucracy to the process.   Arbitration panels also generally are more prone to “split the baby” in a close case.

Which is Better?

The answer to that question is a clear and concise, “it depends.”  It depends on the facts of your particular case, the jurisdiction you are in, the type of panel you may get, and numerous other things completely out of your control.  Consult with a lawyer in your jurisdiction to discuss the pros and cons of each, and which may be right for your particular situation.

Do you have experience with court or arbitration?  Personal preference?  I’d love to hear your thoughts on the subject in the comment section below.

UPDATE 10/13/2010:  The AAA responded to this article citing their internal studies showing arbitration panels do not often “split the baby”.  See more here

_______________

Photo “Courtroom One Gavel” by Joe Gratz via Flickr/Creative Commons license.

Liquidated Damages: what, when, & why

water dropWhat are Liquidated Damages?

Liquidated Damages are a sum which a party to a contract agrees to pay or a deposit he agrees to forfeit, if he breaks some promise.  In the construction realm, liquidated damages (or “LDs”) usually involve money damages for time delays on a construction project.    Typically, a contract will state that time is “of the essence” and that for every day past the scheduled completion date (as modified by change orders & directives) a set amount is due from the contractor to the owner.

When can you get liquidated damages? (or, when must you pay liquidated damages?)

Liquidated damages must be specified in the contract up front.  They should reflect the reasonable estimate of likely damages that will be incurred if the contractor fails to complete the project timely.

To be enforceable, the amount must have been arrived at by a good-faith effort to estimate in advance the actual damage that would likely ensue from the breach, and they cannot be deemed “penalties.”  Eastern Carolina Internal Medicine, P.A. v. Faidas,  149 N.C.App. 940,  564 S.E.2d 53 (2002).

Why?

The purpose of liquidated damages is to reasonably compensate the non-breaching party (typically, the owner for construction delays) which it will likely incur as a result of the breach (e.g., the extended completion date results in lost rent and increase finance charges).  Without the liquidated damages provision, the parties would be forced to argue about each alleged cost the owner incurred because of the delay.  With liquidated damages, the amount is known ahead of time which should (theoretically) lead to fewer arguments later.

When doesn’t the provision work?

Two words—concurrent delay.  If the owner is delaying the project (through, for example, failure to deliver/install owner-provided equipment), but the contractor is also behind on completion, the two delays may run at the same time—hence “concurrent delay”.  In such a situation it becomes difficult if not altogether impossible to separate delays and delay damages.  Of course, if the entire delay is owner-related, no liquidated damages can be assessed.

Take-away message

Liquidated damage provisions, if carefully and properly drafted, are enforced in North Carolina.  You should know your schedule requirements prior to signing on the dotted line and, if necessary, accelerate your work to complete on time.  If you are the owner, however, you also have responsibilities not to interfere with the schedule if you hope to have a chance at recovering liquidated damages from a contractor who delivers a project late.

Questions?  Comments?  Experience with the joys (and sorrows) of LDs?  Share in the comments below.

 __________________________

Photo “Water drop bouncing off the water surface” by konradc via Picasa/Creative Commons License.

Timing can be everything (Tues Tip)

alarm clockIt is always easiest, cheapest, and surest to deal with legal issues right away.   Problems ignored are problems amplified.  A recent North Carolina Court of Appeals cases prove the point:

In the recent NC Court of Appeals case Meier v. City of Charlotte (Aug. 17th, 2010), the Court held that a zoning administrator’s determination could not be appealed because the plaintiff failed to appeal within the 30 days provided by law and, therefore the Board of Adjustment no longer had jurisdiction to hear the appeal.  The petitioners are left to live next to an (allegedly) 50 foot tall house.

This case demonstrates that timeliness is crucial to your case when dealing with the courts.  Don’t delay if you think you have a cause of action, because delay could mean you lose before your case even gets out of the gate.

—————————————–

Photo “Alarm Clock”  by Freefoto.com via Creative Commons License.

Tolling the Statutes of Limitation & Repose? (Law note)

Lowe's Motor Speedway

A blog reader recently raised the question of to how to handle construction defect claims while repair attempts are being made on a defective building.  In part, the answer to this question will depend on how close you are to the statute of limitations or the statue of repose from running.  The closer you are, the more you need to be concerned about this issue.  Just because all parties are working together to solve construction issues does not mean that the statutes are not running.  They can.  [There are, as usual, exceptions for equitable reasons.]  And once statues run, there’s no getting them back.

One prudent approach to dealing with the statutes is to have all parties involved enter into a “Tolling Agreement.”  What a properly drafted tolling agreement can do is to stop the running of the statue of limitations and/or repose while the parties attempt to fix the defects or otherwise settle their issues with one another.  Note that the tolling agreement does not give a party any greater rights than they would have at the time it is signed– that is, if the statute has *already* run, then it would be of no use.  But the tolling agreement can act as a “time out” on the running of the clock.

A good example of a tolling agreements is found in the Court of Appeals opinion in Charlotte Motor Speedway, Inc. v. Tindall Corporation, 195 N.C. App. 296, 672 S.E.2d 691 (2009).  The Speedway case involved the infamous collapse of a pedestrian walkway during the NASCAR Winston Cup.  The walkway which collapsed had been substantially completed by October 1995, and the collapse occurred in May 2000.  Speedway (the project owner) and Tindall (which constructed the walkway) entered into a tolling agreement:

“to toll and suspend any applicable statute of limitations, repose or time, whether created by statute, contract, laches or otherwise, within which any cause, claim action, cause of action, or suit must be made, or commenced by the parties against any one of them concerning the [pedestrian] claims, including any and all claims for indemnification and contribution.”  Id. at 298, 672 S.E.2d at 693.

Tindall attempted to argue that the statute of limitations barred Speedway’s claim for indemnification of monies paid prior to three years before it filed its complaint, but the Court found that the Tolling Agreement, which remained effective “through and including January 1, 2006” tolled the action, and Speedway brought suit on July 17, 2007, less than two years after the Tolling Agreement expired.  Likewise, the Court held that the statute of repose did not bar the action, because the Tolling Agreement was entered into less than six years after substantial completion, and the lawsuit was brought during the pendency of a second funding [tolling] agreement between the parties.

If you are considering a tolling agreement (or think you don’t need one because you “have time”), it is always smart to get a professional opinion on the matter.

______________________________

Comments? Let me know.  I welcome the opportunity to discuss how the statute of limitations and repose may be tolled in your specific situation.