Wine without Cheese? (Why a construction contract needs an order of precedence clause)(Law Note)

wine and cheese

Reader Mailbag:

For today’s law note, I’m addressing a comment that came to me last week from Dave O’Hern of Miller O’Hern Construction.  Dave writes:

I am a general contractor doing a fuel tank replacement project for our county. In the specifications there is a spec for a UL 142 tank, on the plans the spec references UL 2085 – a much more expensive tank. My subcontractor bid the UL 142 tank. The specifications state that the specs and plans are on the same level of precedence.

The county wants me to furnish the more expensive tank without compensation citing the clause that states the plans and specs are complementary and what is called for by one is binding as if called by all and the most stringent requirement will apply.

My position is the word “stringent” according to Websters means “rigidly controlled, enforced, strict, severe.” The two specifications are written by Underwriter’s Laboratory and precisely decribe each type of tank clearly and without ambiguity for the purpose of rigidly controlling the qualities of the product. Consequently the two specifications are equally stringent. Stringent does not mean more expensive or what the pre-bid intent of the owner.

Is this sound reasoning, does it fall under Spearin and is there another defense I should take?

What Dave is experiencing is a poorly-constructed contract.  Obviously, the goal in a set of construction documents is to not have any conflicts.  However, between specifications, drawings, shop drawings, contract language, addendum, and change orders, the goal of absolute consistency in contract documents is impossible extremely hard to meet.

The usual way around this very likely problem is to state the order of precedence of the various contract and construction documents, so that in the event of a conflict between two provisions, everyone knows which one prevails.  In the absence of any contract language stating the order of precedence, the parties are forced to argue contract law principles such as mutual mistake, which party is considered the contract drafter (and hence, disfavored), and other technical legal issues that numb the mind are only exciting to those of us crazy enough to go into the legal profession.

Sure, you can have wine without cheese, but why would you?  The two should go together, in the same way that an order of precedence clause should go with any construction contract.

Dan has also raised the issue of “more stringent” requirements.  In general, when a contract contains instructions that are susceptible to two or more reasonable interpretations, these are considered “ambiguities”.  There is generally a duty on the contractor to point out conflicts between the documents.  However, where a conflict between the documents is not noticed by any party prior to the bidding, the plans arguably are defective under the Spearin doctrine.

So, back to Dan’s question.  Dan– your situation is a mess!  I agree that your reasoning on the stringent requirements is sound; whether or not a Court will agree with your position remains to be determined.  Time to hire a good construction lawyer in your jurisdiction to negotiate a resolution to your situation!  (I see that you are in Arizona.  If you don’t have a lawyer, let me know and I’ll try to get you a recommendation or two).

Have you ever encountered a contract like Dan’s?  Did it cause any problems with conflicting documents later on?  How did you handle the situation?

—————————

 Photo:  054/365: Wine, cheese and crackers via Addison Berry/Creative Commons license. 

Why Misery Loves Company (aka Concurrent delay on the Construction Project) (law note)

You know the old saying, “Misery loves company?”  It’s true.  Even in the construction world.

misery license tag

What happens if, while the design team is asleep at the switch, the contractor is also delaying the project, or the owner is dithering about a materials selection?  Since there was more than one cause of the project delay, does that let you off the hook?  Maybe so.

The above scenario is, in its bare-bones basics, an example of concurrent delay.

What is concurrent delay?  Concurrent delay is delay to the critical path of construction, caused at the same time by multiple events not exclusively within the control of one party.  In other words, it is when two or more parties both contribute to the delay of the project.

In such a case, neither may recover damage from each other, unless there is proof of clear apportionment of the delay and expenses.  See Biemann & Rowell Co. v. Donohoe Cos.,147 N.C. App. 239, 245, 556 S.E.2d 1, 5 (2001).

Where both parties contribute to the delay, neither can recover damages, unless there is proof of clear apportionment of the delay and the expense attributable to each party.  In such an instance, the only remedy for both parties may be an extension of time to the contract.

Have you experienced a case where concurrent delays existed on a Project?  Were you able to apportion the delay damages, or did all the culpable parties pay the price?  Share below. 

Also, please sign up for email delivery of blog posts directly to your inbox!

—————————————

Photo: Misery by Molly Helzschlag via Creative Commons license.

Owner Drafted Indemnity Provisions: Kryptonite for designers?

be careful sign

Be careful with indemnity provisions (and small animals)!

—————————————————————

Are you being asked to sign contracts that are prepared by the Owner?  If so, do you have a policy in place to have each such contract, Master Agreement, or Statement of Work be reviewed by your attorney?  You should.  An ounce of caution is worth a pound of cure, as they say.

One of the most important contract terms to review in any contract is the indemnity provision.  I’ve discussed how indemnity provisions work in the past.  If you haven’t already read that post- do it now.  (Go ahead, I’ll wait).

Today, I want to address indemnity in the context of non-form contracts presented to you by an Owner for execution.  Generally these are presented with no expected negotiation on your part.  Remember, however, that everything can be negotiated.  A few small changes up front can save you lots of time and expense later if there is ever a lawsuit.

Because these contracts are drafted by the Owner (or, rather, his horribly biased zealous attorney), they tend to be overreaching and broad.  Recent contracts I have reviewed ask the architect to indemnify the owner for the design team’s negligence, “regardless of whether or not other parties are also negligent.”  That phrase is very troubling, and should be stricken.  Otherwise, the Owner will have an argument that because the design team was negligent, they must indemnify the Owner for all negligent acts (other than the Owner’s own negligence), including those by other parties.

A better, proportional indemnification provision should include indemnification “to the extent the claim is found to be caused by the negligence of the design team.”  (Even better, of course, would be a limitation of liability based on your design fees, but I recognize that it is often impossible to negotiate such a limitation with some blood-sucking sophisticated Owners.)

Do you have comments about indemnity provisions in contracts you have been asked to sign?  Drop me a note in the comment section, below.

Photo via Creative Commons License.